Transactions of Nonferrous Metals Society of China The Chinese Journal of Nonferrous Metals

您目前所在的位置:首页 - 期刊简介 - 详细页面

中国有色金属学报

ZHONGGUO YOUSEJINSHU XUEBAO

第26卷    第1期    总第202期    2016年1月

[PDF全文下载]        

    

文章编号:1004-0609(2016)-01-0173-07
基于混合整数规划法的采场回采顺序优化分析
王李管1, 2,任助理1, 2,潘传鹏1, 2,陈 鑫1, 2

(1. 中南大学 资源与安全工程学院,长沙 410083;
2. 中南大学 数字矿山研究中心,长沙 410083
)

摘 要: 针对地下矿山传统编制生产计划时存在的随意性大、效率低、不能编制出最优生产计划的弊端,提出运用混合整数规划法解决采场回采顺序优化问题的方法。对无底柱分段崩落法的采场回采顺序进行科学系统的分析,以计划周期内贴现值最大化为目标函数,综合考虑逻辑、设备数量、空间顺序等约束条件,构建采场回采顺序优化的混合整数规划模型;在MATLAB环境下采用YALMIP编写模型语言并调用CPLEX求解器进行求解,进而得到采场回采顺序的最优布置方案。结果表明:此方法科学可行,克服传统手工方法编制生产计划的弊端,实现资源合理高效开采,对指导矿山的实际生产有重要的意义。

 

关键字: 无底柱分段崩落法;采场回采顺序;混合整数规划;生产计划

Optimization analysis of stope mining sequence based on mixed integer programming
WANG Li-guan1, 2, REN Zhu-li1, 2, PAN Chuan-peng1, 2, CHEN Xin1, 2

1.School of Resources and Safety Engineering, Central South University, Changsha 410083, China;
2. Center of Digital Mine Research, Central South University, Changsha 410083, China

Abstract:The traditional analysis process of production schedule is random, inefficient, and the optimal production scheduling can not be arranged. The mixed integer programming method was proposed to solve the stope mining sequence optimization problem. The amount of machinery and equipment, vertical and horizontal mine-sequencing were taken as constraints, the net present value (NPV) was used as objective function of mathematical programming model, the stope mining sequence optimization model was scenically analyzed and built based on mixed integer programming method. It was solved with CPLEX, MATLAB and YALMIP for a certain Chinese iron mine. Finally, the optimal arrangement scheme of stope mining sequence was obtained. The results show that this model is scientific and feasible, and the production schedule saves costs compared to schedules manually by meeting desired production quantities more closely and reducing employee time spent on preparing schedules. It has an important significance to guide the actual production of the mine.

 

Key words: sublevel caving method; mining sequence optimization; mixed integer programming; production scheduling

ISSN 1004-0609
CN 43-1238/TG
CODEN: ZYJXFK

ISSN 1003-6326
CN 43-1239/TG
CODEN: TNMCEW

主管:中国科学技术协会 主办:中国有色金属学会 承办:中南大学
湘ICP备09001153号 版权所有:《中国有色金属学报》编辑部
------------------------------------------------------------------------------------------
地 址:湖南省长沙市岳麓山中南大学内 邮编:410083
电 话:0731-88876765,88877197,88830410   传真:0731-88877197   电子邮箱:f_ysxb@163.com