(1.中南工业大学资源环境与建筑工程 学院, 长沙 410083;
2.铜陵 新桥硫铁矿,铜陵244000)
摘 要: 通过大型采场模型模拟试验,得出了块石胶结充填新工艺实施中的关键技术与参数。据此,在铜陵新桥硫铁矿建成了一套较为完备的块石胶结充填系统,并投入了生产,大大改善了第二步回采的安全,每年可节约充填材料成本达420~500万元,经济效益显著。 该成果将为类似矿山采用这一技术提供了成功的借鉴经验。
关键字: 块石 胶结充填 新桥硫铁矿
(1.College of Resource, Environment and Civil Engineening Central South University of Technology, Changsha 410083 ;
2.Xinqiao Pyrite Mine, Tongling 244000)
Abstract:A qualified cemented rockfill system has been developed in Xinqiao Pyrite Mine according to the key techniques and parameters of cemented rockfill derived from the model test of large stope. The cemented rockfill technique adopted has strengthened the safety of mining and reduced the fill cost about 4.2~5.0 million Yuan per year. The researching result provides a good example for the similar mines to use the technique.
Key words: rock fragment cemented rockfill Xinqiao Pyrite Mine