中国有色金属学报(英文版)
Transactions of Nonferrous Metals Society of China
Vol. 22 No. 3 March 2012 |
(1. School of Resources and Safety Engineering, Central South University, Changsha 410083, China;
2. Hunan Key Laboratory of Resources Exploitation and Hazard Control for Deep Metal Mines Central South University, Changsha 410083, China)
Abstract:Xinli district of Sanshandao Gold Mine is the first subsea metal mine in China. To achieve 6 kt/d production capacity under the premise of safe mining, high-intensity mining might destroy the in-situ stress filed and the stability of rockmass. According to sampling and testing of ore-rock and backfill and in-situ stress field measurement, safety factor method calculation model based on stress-strain strength reduction at arbitrary points and Mohr-Coulomb yield criterion was established and limit displacement subsidence values under the safety factor of different limit stoping steps were calculated. The results from three years in-situ mining and strata movement monitoring using multi-point displacements meter showed that the lower settlement frame stope hierarchical level filling mining method, mining sequence are reasonable and rockmass stability evaluation using safety factor method, in-situ real-time monitoring can provide the technical foundation for the safety of seabed mining.
Key words: subsea bedrock mining; frame stope upward horizontal slicing and filling mining method; safety factor method; multi-point displacement measurement